Location: Denmark
Location: Microgrid
For many years, Bornholm has obtained its electric power via an undersea power cable that connects it with the Nordic grid. The cable was accidentally severed four times in the ten years prior to launching Ecogrid EU, which may have contributed to Bornholm’s readiness to host Ecogrid.The project enable rapid response and increse system reliability when the undersea power cable will be accidentally damaged and to facilitate integration of the large amount of wind power that is locally available.Bornholm Grid 63/11kV7xOHL 63kV11xPower Transformers
Commissioning of protection relays:
- 01
Alstom P545, Alstom P643
- 02
Commissioning Tools: Omicron CMC256